Apr 14, 2014

The Post at Nolan Hill: Construction Update April

I hope everyone is enjoying the spring weather that is finally here. Everyone at The Post in Nolan Hill sure is and we're definitely taking full advantage with construction underway. It was great to visit the site and see we have 2 foundations that already have the foundation walls poured. Now you can start seeing the vision that is The Post at Nolan Hill start to take shape on site!

So what we like to do is break down the construction progress by individual building.

Buildings 1 & 3 - Foundation walls are complete and the ground surrounding the foundation walls has been back filled. Framing will be able to start soon.

Buildings 2, 4 to 7 - Foundation area are to be excavated, then the forms for the foundation walls can go up.

Keep it locked to our Facebook page as we get further into spring - we'll be posting lots of photos from the progress on site!

TaraLynn @ The Post